《Table 3 Removal rate of total Cd and energy consumption after electro-kinetic remediation》

《Table 3 Removal rate of total Cd and energy consumption after electro-kinetic remediation》   提示:宽带有限、当前游客访问压缩模式
本系列图表出处文件名:随高清版一同展现
《Study on Electrokinetic Remediation of Cadmium-contaminated Soil》


  1. 获取 高清版本忘记账户?点击这里登录
  1. 下载图表忘记账户?点击这里登录

The total Cd removal rates and energy consumption of the various groups are shown in Table 3.It could be seen that the energy consumption became larger over time.With the remediation time prolonged from 72 to 96 h,the removal rate of total Cd increased by 6.68%.With the remediation time prolonged from 96 to 120 h,the removal rate of total Cd increased by 8.75%,while when the remediation time was prolonged to 144 h,the removal rate of total Cd only increased by 1.07%.Therefore,comprehensively,the optimal remediation time was 120 h.